Sports facility. Represented contractor in claims against the Owner for cost overruns. Matter successfully settled during trial.
California hospital. Part of a team that obtained a defense verdict, in a four-week arbitration in Los Angeles, for a terminated design-build contractor against a large hospital system owner, with the award setting aside wrongful termination and requiring payment by the owner of extra work claims and contract balance. The dispute included over $100 million of disputed claims involving issues of design errors and omissions, construction workmanship, delay, and wrongful termination.
Breach of contract. Represented a specialty subcontractor as the plaintiff in a breach of contract claim against another subcontractor in a trial in U.S. District Court for the Southern District of Texas, resulting in a complete verdict for the client.
Justice Center projects. Settled over $155 million in disputed claims for a large engineering, procurement, and construction firm working as construction manager for two public projects in Las Vegas involving standard of care of the construction manager, design errors, construction workmanship, terminations, and delay issues.
Refinery. Obtained $1 million in damages, via mediation, for a refinery owner against a pressure vessel fabricator involving defective welding and non-destructive examination (NDE), which failed to meet ASME VIII Code requirements.
Design professionals. Represented an architect in the defense of an owner’s claims of errors and omissions.
Mechanic’s liens. Represented numerous suppliers, subcontractors, and general contractors in mechanic’s liens and breach of contract actions. Represented owners in defense of mechanic’s liens filed against the owner’s property.
Experience
Sports facility. Represented contractor in claims against the Owner for cost overruns. Matter successfully settled during trial.
California hospital. Part of a team that obtained a defense verdict, in a four-week arbitration in Los Angeles, for a terminated design-build contractor against a large hospital system owner, with the award setting aside wrongful termination and requiring payment by the owner of extra work claims and contract balance. The dispute included over $100 million of disputed claims involving issues of design errors and omissions, construction workmanship, delay, and wrongful termination.
Breach of contract. Represented a specialty subcontractor as the plaintiff in a breach of contract claim against another subcontractor in a trial in U.S. District Court for the Southern District of Texas, resulting in a complete verdict for the client.
Justice Center projects. Settled over $155 million in disputed claims for a large engineering, procurement, and construction firm working as construction manager for two public projects in Las Vegas involving standard of care of the construction manager, design errors, construction workmanship, terminations, and delay issues.
Refinery. Obtained $1 million in damages, via mediation, for a refinery owner against a pressure vessel fabricator involving defective welding and non-destructive examination (NDE), which failed to meet ASME VIII Code requirements.
Design professionals. Represented an architect in the defense of an owner’s claims of errors and omissions.
Mechanic’s liens. Represented numerous suppliers, subcontractors, and general contractors in mechanic’s liens and breach of contract actions. Represented owners in defense of mechanic’s liens filed against the owner’s property.